1.5 Partnering Requirements During Construction
All projects with a construction cost estimate of $10,000,000 or more shall require “Partnering” during construction. The Partnering shall involve representatives from the design consultants, the program manager, the construction manager, the contractor, and the MDOT MAA.
The intent of this program is to initiate project culture change by developing team goals, assess overall project tasks and manage conflict resolution expeditiously. The Consultants must identify and incorporate the fee associated with participating in partnering during construction in their design fee proposal under their Phase III services.
The Consultants shall also incorporate the appropriate specifications and requirements in all construction contract specifications which have a construction cost estimate of $10,000,000 or more, requiring the contractor to engage in “Partnering” sessions and activities as required and scheduled by MDOT MAA or its representative.