1.2 Office of the Fire Marshal Shop Drawing/Submittal Review
During construction, the Construction Manager will forward a copy of the appropriate shop drawing/submittals to the Fire Marshal at the same time they are sent to the Consultant. The Construction Manager will then schedule a meeting one week later with the Fire Marshal, Consultant, Construction Manager, and MDOT MAA Office of Engineering & Construction. At that meeting, all shop drawing issues will be addressed, and a decision will be rendered as to the status of the submittal and noted on the MDOT MAA stamp shown below. The shop drawings/submittals will be returned to the Construction Manager at that time for further action.
The shop drawing/submittal review meeting will also provide an opportunity for the Consultant, Construction Manager, and Fire Marshal to review contract revisions and modifications.