SECTION 8 EXECUTION AND PROGRESS
SP-8.00 Project Scheduling Requirements
A. The Contractor shall develop project schedules fully conforming to the requirements of Special Provision: SP-8.03-Critical Path Method Schedules.
B. The Contractor will develop and submit a project CPM schedule, consisting of Detailed Schedules #1, after issuance of a “Notice of Recommended Award” (NORA), as required in the Project CPM Development and Submission Table (“Table”) below. This schedule is subject to the review and acceptance process set forth in the Table and the times prescribed therein are of the essence.
C. The Administration will execute the Contract and issue a "Notice to Proceed" (NTP) for the project only if the Administration accepts the Contractor's Detailed Schedules #1. If acceptance of the Detailed Schedules #1 or #2 occurs after the time specified in the Table due to late or nonconforming submissions by the Contractor, the Contract Performance Time specified elsewhere in the Contract shall be reduced by the number of days of delay in acceptance of Detailed Schedules #1 or #2 caused by late or nonconforming schedule submissions.
D. For purposes of developing the project CPM schedule submissions in accordance with the Table, the Contractor shall use a Notice to Proceed date that is issued within one hundred and twenty (120) days after the “Notice of Recommended Award” date. Within seven (7) days after a “Notice to Proceed” is issued, the Contractor will resubmit the approved project CPM schedule incorporating the actual “Notice to Proceed” date and reflecting any adjustments to Contract Performance Time pursuant to paragraph C above.
E. If any Detailed Schedule submission is late or, if the Administration determines that the Contractor will not reasonably complete the project within the reduced Contract Performance Time, in addition to any other remedies available to it, the Administration may terminate the Contractor’s right to proceed with the Contract for default pursuant to General Provision: GP-8.08-Termination for Default-Damages for Delay-Time Extensions. If the Contract is not executed for reasons unrelated to submission, review, and acceptance of the Project CPM Schedule, the Administration shall reimburse the Contractor its actual costs of developing the Project CPM Schedule.
Project CPM Schedule Development and Submission Table I:
Activity / Submission Description |
Working* Days Due From NORA |
Notice of Recommend Award (NORA) Issued |
0 |
Contractor Designates Scheduling Representative |
1 |
Schedule Requirements Review Meeting |
3 |
Schedule Format Review Meeting |
8 |
Contractor’s Initial Detailed Schedule #1 Due |
18 |
Contractor’s Schedule Presentation to Engineer |
20 |
Engineer’s Review of Initial Detailed Schedule #1 Due |
25 |
Contractors Final Detailed Schedule #1 Due |
30 |
Engineer’s Review of Final Detailed Schedule # 1 Due |
35 |
Planned Acceptance of Detailed Schedule #1 (Required prior to issuance of NTP |
35 |
Project CPM Schedule Development and Submission Table II:
Activity / Submission Description |
Working* Days Due From NTP |
Contractor’s Initial Detailed Schedule #2 Due |
10 |
Engineer's Review of Initial Detailed Schedule #2 Due |
15 |
Contractor’s Final Detailed Schedule #2 Due |
20 |
Engineer's Review of Final Detail Schedule #2 Due |
25 |
Planned Acceptance of Detailed Schedule #2 (Required prior to 1st Progress Payment) |
25 |
*Based on five day work week
A. Notwithstanding GP-8.01, the Contractor must submit, with Contract Forms, a "Subcontractor Utilization Form" for assignment or disposition of work under his/her Contract. A sample "Subcontractor Utilization Form" is included under Contract Forms, Section 7.
B. In accordance with GP-8.01, Subcontracting, within fourteen days (14) after award of the Contract, the Contractor shall deliver to the Engineer a completed Statement of Acknowledgement Form for each subcontract. This form, signed and dated, acknowledges that all of the applicable Standard Provisions, indicating Volume and Date, and applicable Technical Provisions has been included in the subcontract.
C. A sample "Subcontractor Statement of Acknowledgement Form" is included under Special Provisions, Section 10, SP-10.03, and in the Technical Provisions.
D. Within fourteen (14) days after the award of any subsequently awarded subcontract, the Contractor shall deliver to the Engineer an updated form for each additional subcontract.
SP-8.02 Schedules
A. The Contractor shall submit, within thirty (30) days from the date of the Notice‑to‑Proceed, a progress schedule in accordance with Section GP-8.04, Progress Schedule. This schedule shall be updated and revised to reflect all changes affecting the job progress. The prosecution of the work shall always be under the direction of the Engineer. The Contractor shall work at as many different points, in such part or parts, and at such times as may be directed.
B. If in the opinion of the Engineer, an immediate need exists for a schedule of submittal and construction activities, the Contractor shall prepare for review and approval an interim schedule for the first sixty (60) days of operation. The interim schedule will be required to be submitted in accordance with all requirements of this section and of GP-8.04, Progress Schedule.
C. The work schedule to be submitted by the Contractor, as provided in the subsection of the GP-8.04, Progress Schedule, shall be so prepared and the proposed work shall be so conducted as to interfere as little as possible with other construction work, and vehicular traffic. The schedule shall be satisfactory to the Engineer. The Contractor shall submit a schedule based on area sequencing and phasing as well as by construction elements. The Engineer may withhold all monies due, or to become due, the Contractor for partial payments until a work schedule is received and approved by the Engineer.
D. The progress schedule shall graphically indicate by the use of bars, lines, or other conventional methods, phasing of all work and related operations. The Contractor shall show, thereon, dates and the number of days proposed to complete the major operations involved in this Contract. He/she shall also show the relationship of working days to total earnings. The schedule shall also include dates when Shop Drawings and related Working Drawings as well as informational data shall be required under the various headings of the Specifications to be submitted to the Engineer for approval. The schedule shall provide adequate time for review and approval with the entire submittal procedure coordinated through the Engineer. The schedule shall be updated and revised on a regular basis incorporating any changes and shall reflect any delays or escalation affecting job progress.
E. During the progress of the work, it may be necessary for the Engineer to adjust the approved schedule to better suit Airport Operations. In addition, other contracts may be under construction concurrently with this Contract, and the Contractor shall coordinate his/her work as required in GP-5.06, Cooperation Between Contractors. The Contractor shall cooperate fully with the Engineer and user agencies in the programming of his/her work to insure the uninterrupted functioning of services essential to the operation of the Airport and the maintenance of security measures.
F. When specified in the Technical Provisions, the Contractor shall develop Critical Path Method Schedules (CPM) in accordance with the requirements set forth under Special Provisions, Section SP-8.03, Critical Path Method Schedules.
SP-8.03 Critical Path Method Schedules
A. General:
The requirements for the Critical Path Method Schedule included in this section shall supersede General Provision: GP-8.04-Progress Schedules.
1. Careful evaluation and pricing of the schedule provisions of this Contract are important to assure compliance with the language and intent of the schedule specification. The schedule provisions are designed to provide the Contractor and the Administration with a tool for planning and controlling the work. The schedule provisions must be strictly followed to insure both timely progress payments and equitable compensation for changes and delays. The Contractor must perform work in accordance with the approved Critical Path Method (CPM) Schedule to achieve timely completion of all Contract milestones and to avoid acceleration, termination for default, and end of Contract claims for liquidated damages. The Contractor must give the schedule provisions particular consideration and resolve any areas of uncertainty by asking appropriate questions prior to bid opening.
The schedule submission times shall be as specified in the “Project CPM Development and Submission Table” included in the solicitation documents under section SP-8.00-Project Scheduling Requirements.
2. The Contractor shall provide CPM schedules as defined in the following criteria.
a. The purpose of the Project Schedule shall be to:
(1) Assure adequate planning, scheduling and reporting during execution of the work by the Contractor;
(2) When more than one Prime Contractor is working at a site, assure coordination of the work of the Contractor and the various subcontractors and suppliers at all tiers;
(3) Assist the Contractor and Engineer in monitoring the progress of the work and evaluating proposed changes to the Contract and the Project Schedule;
(4) Assist the Engineer and the Contractor in the preparation and evaluation of the Contractor's monthly progress payments;
(5) Provide information to the Engineer enabling the timely coordination of work activities involving Tenants and/or impacting Airport or Tenant operations; and
(6) Assist the Engineer in determining required dates for owner supplied materials and services.
b. The Project Schedule shall employ the CPM using retained logic for the planning, scheduling and reporting of the work to be performed under the Contract. Start and finish dates in the schedule shall be calculated by schedule logic and activity durations, not by resources or non-contractual constraints. All activity codes and calendars used shall be project-level. The schedule will be produced utilizing the most current version of Primavera P6 software system, or fully transferable to P6 (refer to "Products (Scheduling Software)" in Section K of this Provision). Definitions applicable to this Provision include the following:
(1) Project Schedule: The Project Schedule includes the electronic XER file;
(2) Critical Path: The Critical Path is the sequence of the activities in the Project Schedule network which requires the longest total amount of time to complete the work or any path(s) which have total float less than one (1) working day;
(3) Time Scale Logic Diagram: The Time Scale Logic Diagram (TSLD) is the graphic representation of the Project Schedule prepared as an 11” x 17” electronic (.PDF) format using the CPM. The TSLD shows the sequence and interdependence of the activities, and planned and actual progress by activity, required for complete performance of the work. The columns shown shall include the activity ID, activity description, original duration, remaining duration, early start and finish, late start and finish, actual start and finish, and total float, or as requested by the Engineer;
(4) Working Day: A working day is any calendar day scheduled for active performance of Contract requirements; and
(5) Key Plans: Graphic representations of the Contractor's planned breakdown of the project for scheduling purposes. The key plans will clearly define the boundaries of the work for each designated area. The boundaries of each area may change depending on the phase of construction. The alphanumeric codes on the key plans shall match the code values for the "Area" in the schedule.
c. The Contractor shall provide Time Scale Logic Diagrams as stipulated herein, at no additional cost to the Administration.
d. The Contractor shall meet with the Engineer per the Project CPM Development and Submission Table to conduct a joint review of the Project Schedule requirements of the Contract to assure the Administration of the Contractor and subcontractor's understanding of the requirements of this Section. Refer to "Schedule Approval Process" under this item.
e. Per the Project CPM Development and Submission Table, there will be a formal presentation by the Contractor of its intended prosecution of the project. The Contractor's Management Team and Scheduling Representative shall conduct the formal presentation utilizing schedule graphics and charts of the approach the Contractor will take to complete the project within the contractual milestones. The Contractor shall provide electronic (.PDF) format of the proposed key plans of the project and each structure for each phase throughout the duration of the project. The Contractor shall also provide proposed codes and code values of activities for the project. The key plans and coding descriptions shall match exactly.
3. Contractor's Scheduling Representative:
a. Per the Project CPM Development and Submission Table, the Contractor shall designate in writing an authorized representative in the Contractor's organization (Scheduling Representative) who shall be responsible for preparation and maintenance of the Project Schedule. The Contractor may not replace the Scheduling Representative without prior written consent of the Engineer,
b. The Contractor shall submit the qualifications of the Scheduling Representative to the Engineer for approval. The approval is required before the Detailed Schedule #1 will be accepted. The Scheduling Representative shall have at least five years of verifiable experience for preparing and maintaining CPM project schedules in Primavera P6 on contracts of similar size and complexity.
c. The Scheduling Representative shall have complete authority to act on behalf of the Contractor in fulfilling the Project Schedule requirements of the Contract and such authority shall not be interrupted throughout the duration of the Contract unless approved in writing by the Engineer.
d. The Scheduling Representative shall attend all schedule-related meetings and all monthly update meetings throughout the duration of the Contract in addition to the General Superintendent.
e. The Contractor agrees that whenever the Engineer advises the Contractor in writing that the Scheduling Representative is not performing his/her duties to the satisfaction of the Administration, the Contractor shall replace the Scheduling Representative at no additional cost to the Administration and designate in writing, within seven (7) calendar days, a new authorized representative satisfactory to the Engineer.
4. Schedule Requirements review Meeting
At the Schedule Requirements Review Meeting, the Engineer will review in detail the scheduling requirements contained in the specifications.
5. Schedule Format Review Meeting
At the Schedule Format Review Meeting, the Contractor will present to the Engineer the Format of the schedule developed to that point. Format includes: Activity Coding Structure, calendars, prototype activity descriptions, logic and graphical presentations.
B. Detailed Schedule #1:
1. Per the Project CPM Development and Submission Table I, the Contractor shall submit a Detailed Schedule #1 showing all work to be accomplished on the project. Detailed Schedule #1 shall include, but not be limited to, the following:
a. Procurement activities:
The proposed procurement activities shall include mobilization, shop drawings and sample submittals, fabrication and delivery of key and long-lead procurement elements. The schedule shall indicate intended submittal dates and realistic delivery dates for fabrication and delivery activities.
(1) The Administration’s review of: shop drawings, product data, samples and requested substitutions shall be identified as schedule activities. The minimum duration for these activities shall be twenty-one (21) calendar days for shop drawings, product data and samples and forty-five (45) calendar days for requested substitutions in accordance with Special Provisions: SP-8.06-Submittals (Shop Drawings, Product Data and Samples) and SP-5.04-Request For Substitutions.
(2) In the event a submittal is rejected or returned for correction, a new activity will be inserted into the schedule for Resubmission and another for Review of the Resubmission.
b. Construction activities:
(1) The construction activities shall cover all physical work activities performed by the Contractor and subcontractors.
(2) The construction activities shall also cover all work to be performed by the Administration or its contractors related to the Contract.
c. Milestone events as required by the Contract Documents.
d. Commissioning activities, as separate activities, shall show:
(1) All training activities required by the contract prior to project or phase substantial completion; and
(2) All testing activities required by the contract prior to project or phase substantial completion.
2. The Time Scale Logic Diagram (TSLD) shall show the sequence and interdependence of activities required for complete performance of the work. The Contractor shall be responsible for assuring all work sequences are logical and the TSLD shows a coordinated plan of the work.
3. The time duration assigned to each activity shall be the Contractor's best estimate of working days required to complete the activity considering the scope and resources planned for the activity and shall be limited to a maximum of fifteen (15) working days for each activity. The minimum time duration shall be one (1) working day.
4. Anticipated lost time due to weather shall be included in the Schedule to ensure completion of all work within the Contract time. These days will be eliminated from the Schedule's work calendar and spread over each month. The days eliminated may not coincide with holidays or other days that would already be non-workdays. Individual activity durations are not to be increased to include expected lost weather days. Special Provision: SP-8.10-Time Extensions for Unusually Severe Weather, sets out the maximum number of days expected to be lost assuming a five day work week. Time extensions for abnormal weather will only be granted when the actual lost days exceed the maximum number, and are not compensable. The Contractor's incorporation of the anticipated lost weather days must be acceptable to the Engineer. Time extensions for unusually severe weather beyond the contractual completion date will not be granted if the contract duration has extended beyond the contractual completion date due to contractor delay.
5. Restrictions on all temperature-sensitive construction activities shall be included in the Schedule. The Contractor’s incorporation of these restrictions into the schedule must be acceptable to the Engineer.
6. In developing the Schedule, the Contractor shall be responsible for assuring that subcontractor and supplier work at all tiers, as well as its own work, is included in the Schedule.
7. The following shall be depicted on the Network for each activity:
a. Concise description of the work represented by the activity (maximum 120 characters). The work related to each activity shall be limited to one work trade and one floor or other building as required by the Specifications. Activity descriptions shall include verbs and shall quantify the work where possible;
b. Activity duration in whole working days with a minimum duration of one (1) workday and a maximum duration of fifteen (15) workdays each, unless otherwise approved or directed by the Engineer, except for non-construction activities including mobilization, shop drawing and sample submittal, fabrication of materials, delivery of materials and equipment and concrete curing;
c. Work area project-level activity code for construction activities (maximum 20 characters). All abbreviations shall be fully described in a legend attached to the Time Scale Logic Diagram. As requested by the Engineer, either prior or subsequent to the acceptance of the Schedule, the Contractor shall provide, without additional cost to the Administration, a graphic illustration of the relationship of construction activities to intended work areas as identified by the Contractor on prints of the Contract Drawings;
d. Performance responsibility by discipline project-level activity code: MECH, ELEC, etc., or other acceptable abbreviations approved by the Engineer (maximum of 20characters). Each subcontractor shall be coded separately. Include activity code values for MBE and non-MBE subcontractors. All abbreviations shall be fully described in a legend attached to the Time Scale Logic Diagram;
e. A project-level activity code that shall identify the specification number appropriate to the activity.
f. A project-level activity code that shall identify the phase of the project in which the activity is to be performed.
g. A project-level activity code that differentiates between submittal/procurement activities and construction activities.
h. Each submission of Detailed Schedule #1 shall include:
(1) All schedule information in electronic (.XER) format as directed by the Engineer.
(2) An electronic (.PDF) file format of its proposed Detailed Network (Time Scale Logic Diagram) sorted by Early Start of all activities.
(3) A written Narrative that shall present the construction approaches and explains the schedule logic. It shall discuss the project's critical path. It shall state how the Contractor plans to work the project (days/shifts/hours). It shall give the expected number of lost working days to weather for each month and discuss how the Schedule calendar accounts for these lost days. It shall present any temperature restrictions included in the schedule.
i. If the Engineer questions the Contractor's proposed activities, logic, or durations, the Contractor shall provide a satisfactory revision, or adequate justification, to the satisfaction of the Engineer.
j. Failure by the Contractor to include any element of work required for performance of the Contract shall not excuse the Contractor from completing all work within the Contract time.
k. The approved Detailed Schedule #1 shall become the baseline project schedule for logic and durations.
l. Detailed Schedule #1 shall have a data date of the Notice of Recommended Award, or as directed by the Engineer.
C. Detailed Schedule #2:
1. Per the Project CPM Development and Submission Table II, the Contractor will submit Detailed Schedule #2 which shall include all appropriate cost, manpower, and if specifically requested, major equipment requirements for the schedule activities. Detailed Schedule #2 shall utilize the approved Detailed Schedule #1 as the base schedule and add resource and cost loading as detailed below.
2. Detailed Schedule #2 shall use the same state date as Detailed Schedule #1 and shall incorporate the actual Notice to Proceed date into the schedule.
3. The following shall be incorporated into the Network for each construction and appropriate procurement activity:
a. For Lump Sum contracts, the assigned dollar value of each activity in the Network, shall represent its labor, material and equipment costs. Activity cost estimates shall correlate with, the breakdown of the total Contract price as shown in the Detailed Schedule of Values (See Part I, General Information Section of Plans & Specifications). Each subcontractor’s overhead and profit, mobilization and demobilization, bond and insurance costs shall be allocated between its activity costs (labor and materials). The total for all activities representing work for a given specification section shall cumulatively equal the sum of the labor and material amounts shown for that specification section in the Detailed Schedule of Values. The General Contractor’s general conditions, overhead and profit, mobilization and de-mobilization, quality control program, bond and insurance costs shall not be included in the activity costs but shall be shown as separate Level of Effort activities in the Schedule and conform to the approved Detailed Schedule of Values.
b. For unit price contracts, or for unit price activities of an otherwise Lump Sum contract, the assigned value of each activity shall represent the expected costs (covering labor, material and equipment) based on the expected quantity of material estimated for the activity and its quoted unit price. The activity's quantity shall be shown on the Network and shall also be included in the activity's description. Project mobilization, bond, insurance costs, overhead and profit shall not be included in the activity costs nor separately in the Network (and shown separately in the Schedule of Values).
c. The manpower loading of each activity in the Network, for a fixed or unit price contract, shall be the total number of man hours of each activity. For a fixed price contract, the total number of man hours assigned to the Network shall correlate with the labor costs in the Schedule of Values for each subcontractor's work.
d. For cost loading purposes, fabrication activities will not be cost loaded but delivery activities may be.
4. Each submission of Detailed Schedule #2 shall include:
a. All schedule information in electronic (.XER) file format as directed by the Engineer.
b. An electronic (.PDF) file format of its proposed Time Scale Logic Diagram sorted by Early Start of all activities.
c. A written Narrative presenting the cost, manpower and equipment information in summary form and discussing any anticipated problems with attainment of the required levels.
D. Engineer Reviews, Joint Reviews, Revisions and Acceptance:
1. The Engineer will review the initial submissions of the Detailed Schedule #1 and Detailed Schedule #2 and will respond with comments in accordance with the Project CPM Development and Submission Table. The Engineer and the Contractor shall meet in accordance with the Project CPM Development and Submission Tables for joint review, correction or adjustment of the Detailed Schedule #1 and #2. Any areas which, in the opinion of the Engineer, conflict with timely completion of the Contract shall be subject to revision by the Contractor.
2. In the event the Contractor fails to define any element of work, activity, or logic and the Engineer’s review does not detect this omission or error, such omission or error, when discovered by the Contractor or the Engineer, shall be corrected by the Contractor at the next monthly Schedule Update (as discussed hereinafter) and shall not affect the Contract time.
3. As required by the Project CPM Development and Submission Tables, the Contractor shall revise the Schedule in accordance with agreements reached during the joint review meetings and submit in electronic file format as directed by the Engineer.
4. In the event that Detailed Schedule #1 indicates the Contractor's plan to finish prior to the Contract completion date, the Contractor and the Administration shall execute a change order adjusting the Contract completion date to coincide with the Contractor's planned finish date at no expense to the Administration. Liquidated Damages will be measured from the adjusted Contract completion date.
5. Acceptance by the Engineer of the Contractor's approved Project Schedule will be a condition precedent to issuance of a Notice to Proceed, and the making of any progress payments under the Contract.
6. Upon acceptance of the Project Schedule by the Engineer, the cost-loaded values of the Project Schedule will be used as a basis for determining progress payments. Monthly progress payments shall be based upon information developed in the monthly Schedule Update. The computer-produced Cost Report will be utilized by the Engineer for verification of the Application for Payment submitted by the Contractor. Acceptance by the Engineer of the Contractor's Project Schedule does not relieve the Contractor of any responsibility whatsoever for the accuracy or feasibility of the Project Schedule, or of the Contractor's ability to meet the Contract Completion Date. Nor does such acceptance create a warranty, expressed or implied, or acknowledge or admit the reasonableness of the activities, logic, durations, manpower, cost of equipment loading of the Contractor's Project Schedule.
E. Project Schedule Updating:
1. The Project Schedule shall be updated on a monthly basis throughout the entire Contract time and until the Contract's Substantial Completion. The Contractor shall meet with the Engineer each month at the Schedule Update meeting to review actual progress made through the data date of the Schedule Update, including dates activities started and/or completed, and to discuss the scheduling of future work. Revisions to the Network logic to more accurately reflect the anticipated workflow can be discussed and mutually agreed-to, as well as changes to activity durations, staffing and equipment. The data date of each Schedule Update, which shall be the effective date of the Progress Payment Request, shall be on or before the seventh (7th) day preceding the progress payment submittal deadline. Contractor-prepared estimates of the percent completion of each schedule activity and the necessary supporting cost data shall be presented at the update meeting and shall include the following information:
a. The previous month's Schedule Update in both electronic (.XER) file format and electronic (.PDF) file format updated to indicate the progress on schedule activities and the revised (current) remaining durations.
b. The previous month's Schedule Update must indicate actual activity start and/or complete dates, revised (current) remaining durations, and percent complete with regard to activity cost/progress.
c. A listing of proposed activities to be added together with predecessors and successors, duration, manpower and cost.
d. A listing of proposed activities to be deleted.
e. Any additional written information necessary to support the above.
2. In case of disagreements at the schedule update meeting, concerning actual progress to date, the Engineer's determination shall govern.
3. Upon completion of the schedule update meeting, the Contractor shall revise the Project Schedule to reflect progress as of the data date of the Schedule Update and carry out a computer-produced calculation to determine the status of the Project Schedule. This progress only schedule will be considered the A-Schedule. The Contractor shall use the A-Schedule and make any required revisions to the Project Schedule and carry out a computer-produced calculation to determine the status of the Project Schedule. This revised schedule will be considered the B-Schedule. The Contractor shall process the A and B-Schedules. The Contractor shall process the A and B Schedules within three (3) calendar days and forward the update and pay request to the Engineer. The Engineer shall review the update upon receipt, and shall process the monthly request for payment based upon the accepted update.
4. Each Project Schedule Update, based upon the Contractor's input as discussed above, will be forwarded to the Engineer and will include the following information:
a. A written Narrative summarizing schedule status and providing the following detailed information:
(1) A listing and explanation of activities added and deleted.
(2) A listing and explanation of logic changes (overlapping, etc.)
(3) A comparison of actual manning and equipment usage to the requirements of the previous update.
(4) A discussion of possible recovery actions to counter any schedule slippage. In the event that schedule slippage exceeds twenty-one (21) calendar days, this portion of the Narrative will be comprehensive. If it is not, then the Engineer may reject the schedule update and delay processing of the monthly Pay Request.
b. The latest schedule update, including the separate A and B-Schedules, in electronic file format as directed by the Engineer.
c. An electronic (.PDF) file format of the current Network (Time Scale Logic Diagram) sorted by Early Start of all activities.
d. The monthly updating of the Project Schedule shall be an integral part and basic element of the estimate upon which progress payments will be made. If, in the judgment of the Engineer, the Contractor fails or refuses to provide information required to accomplish a complete Project Schedule Update or revision as specified hereafter, the Contractor shall be deemed to have not provided the required estimate upon which progress payments may be made, and shall not be entitled to progress payments until it has furnished the information necessary for a complete Schedule Update to the satisfaction of the Engineer.
F. Project Schedule Revisions:
1. Updating the Project Schedule to reflect actual progress made up to the date of a Schedule Update shall not be considered a revision to the Project Schedule.
2. The Contractor may also request revisions to the Project Schedule in the event the Contractor's planning of the work is revised. If the Contractor desires to make changes in the Project Schedule to reflect revisions in its method of performing the work, the Contractor shall notify the Engineer in writing at least seven (7) calendar days prior to the next Schedule Update meeting, stating the reason for, and describing, the proposed revisions. Accepted revisions will be incorporated into the Project Schedule at the next monthly Schedule Update.
3. If the Engineer believes that the Project Schedule needs a specific revision, either in logic, activity duration, manpower or cost, it will be requested from the Contractor in writing. The Contractor shall respond in writing within seven (7) calendar days, either agreeing with the Engineer's proposed revision, and henceforth including it in the next Project Schedule Update, or setting forth justification why it should not be accomplished. If the Contractor's justification for not accomplishing the revision is accepted, such revision will not be incorporated into the next update of the Project Schedule. The Contractor's failure to respond in writing within seven (7) calendar days will be deemed to be an acceptance of the Engineer-requested revision, and such revision shall be incorporated into the next Project Schedule update.
G. Recovery Schedule
1. If, as a result of the Project Schedule Update, it appears that the Project Schedule as shown no longer allows attainment of the Project completion date, the Engineer will request, and the Contractor shall submit, a recovery schedule sufficiently explaining, detailing, and displaying to the Engineer’s satisfaction, how the Contractor intends to reschedule its work in order to regain the contractual requirements, all without additional cost to the Administration. This may require the Contractor to increase the number of shifts, initiate or increase overtime operations, increase days of work in the work week, or all of them.
2. The Engineer shall make his request in writing within five (5) calendar days of receiving the monthly update. The Contractor shall submit this recovery schedule at least five (5) calendar days before the next scheduled update meeting so that the Engineer may review and accept it for use in the next schedule update.
H. Time Impact Analysis for Proposed Change Orders and Delays:
1. When the Contractor desires to obtain an extension of the project duration because of a change order or other occurrence on the project, the Contractor shall submit to the Engineer a written Time Impact Analysis illustrating the influence of the change order or occurrence on the Contract Schedule. Each Time Impact Analysis shall include a Fragmentary Network (FragNet) demonstrating how the Contractor proposes to incorporate the change order or occurrence into the Project Schedule. The Time Impact Analysis shall demonstrate the time impact based on the date the change order was given to the Contractor or the date of the occurrence; the status of construction at that point in time; and the event time computation of all affected activities. Upon approval by the Engineer, the change order or occurrence shall be included in the next Project Schedule update.
2. Activity delays shall not automatically mean that an extension of the Contract time is warranted or due the Contractor. It is possible that a change order or occurrence will not affect existing critical activities or cause non-critical activities to become critical. A change order or occurrence may result in only absorbing a part of the available total float that may exist within an activity chain of the Network, thereby not causing any effect on the Contract time.
3. Float is not for the exclusive use or benefit of either the Administration or the Contractor. Extension of the Contract time will be granted only to the extent the equitable time adjustments to the activity or activities affected by the change order or occurrence exceeds the total float of a critical activity (or path) and extends the Contract time set forth in the General Provisions: GP-8.03-Prosecution of the Work, and GP-8.09-Liquidated Damages.
4. Submit Time Impact Analysis in accordance with the following along with a written proposal for any requested time extension;
a. Within seven (7) calendar days after receipt of a written change order pursuant to General Provision: GP-4.06-Changes and Special Provision: SP-9.04-Negotiated Payment.
b. Within ten (10) calendar days from the beginning of a delay from unforeseeable causes pursuant to General Provisions: GP-4.05-Differing Site Conditions, GP-8.07-Suspension of Work, and/or GP-8.08-Termination for Default-Damages for Delay-Time Extensions.
c. With the filing of a written notice of claim pursuant to General Provision: GP-5.14-Claims.
5. In cases where the Contractor does not submit a Time Impact Analysis within the time requirements stated above, it shall be considered a waiver of any request for an extension of the Contract Performance Time. Any subsequent Time Impact Analysis submitted by the Contractor shall be dismissed by the Procurement Officer as untimely.
6. Approval or rejection of each Time Impact Analysis by the Engineer shall be made within seven (7) calendar days after receipt of each Time Impact Analysis, unless subsequent meetings and negotiations are necessary. Upon approval, a copy of the Time Impact Analysis signed by the Engineer shall be returned to the Contractor, and incorporated into the next Project Schedule Update.
7. The Time Impact Analysis related to a change order shall be incorporated into and attached to the applicable change order.
I. Responsibility for Completion:
1. The Contractor shall furnish sufficient forces, offices, facilities and equipment, and shall work such hours including night shift and overtime operations, as necessary to ensure the prosecution of the work in accordance with the current monthly Project Schedule Update. If the Contractor falls behind in meeting the Project Schedule as denoted by negative float in the current monthly Project Schedule Update, at the direction of the Engineer, the Contractor shall take such steps as may be necessary to improve its progress. Determining the justification of additional payment to the Contractor for such actions shall not be a precursor for these actions. The provision of this paragraph shall not be construed as prohibiting the Contractor from increasing the hours of work, the number of shifts, overtime operations and/or the amount of construction plant and equipment or working on Saturdays, Sundays and holidays, provided the Contractor gives reasonable notice to the Engineer as required under Special Provisions: SP-7.03-Night Work and SP-7.04-Saturday, Sunday, and Holiday Work.
2. Failure of the Contractor to comply with the requirements of paragraph H.1 above shall be a basis for determination by the Engineer that the Contractor is not prosecuting the work with such diligence as will ensure completion within the Contract time. Upon such determination, the Engineer may terminate the Contractor's right to proceed with the work or any separable part thereof, in accordance with the General Provision: GP-8.08-Termination for Default, Damages for Delay - Time Extensions, or may take such other actions as may be deemed appropriate.
J. Performance Monitoring:
1. The Engineer may elect throughout, or at any time, during the Contract to record the number of workers and construction equipment working on each schedule activity in each area of the Contract and give a copy of this log to the Contractor who shall be responsible for advising the Engineer, without additional cost to the Administration, of any error in this work history, in writing, within seven (7) calendar days of receipt of same. This information will be used by the Engineer in its evaluation of the adequacy of the Contractor's performance and on-site manpower staffing, as well as in the evaluation of any Contractor requests for additional payment.
2. For certain critical work, the Engineer may require that the Contractor submit each Monday morning (or following day if a holiday), a Status Report of all progress which has occurred in any schedule activity, including:
a. Percent Complete; and
b. Actual Start/Finish Dates.
3. This Status Report shall also indicate which activities the Contractor plans to start, or to continue during that week. This Status Report shall serve as a basis for discussion at the next project progress meeting. These actual start and finish dates and percentages of completion estimates will be used by the Engineer to evaluate the monthly Project Schedule Update.
K. Completion Schedule:
1. No later than sixty (60) days prior to the scheduled completion of the Project, the Contractor shall prepare and submit a detailed Completion Schedule to the Engineer for approval. This Completion Schedule shall indicate all remaining work under the Contract, grouped by designated areas, and shall be derived from the most recent monthly Project Schedule Update.
a. The designated areas for reporting shall be determined by the Engineer and shall be as detailed as may be required by the Engineer to facilitate coordination with the tenants, final testing, final inspections, and acceptance of the facility for maintenance pursuant to General Provision: GP-5.13-Acceptance for Maintenance and Special Provision: SP-8.09-Project Completion and Punchlist.
b. The Completion schedule shall be in the form of a computer-generated listing, which shall include every activity with work remaining in each designated area. Each activity listed shall only represent work by one trade/subcontractor. Estimated remaining manhours shall be shown for each activity listed.
2. The Contractor shall submit the Completion Schedule together with a written narrative that summarizes the manhours of effort required for completion of the project, itemized by the Contractor’s work force and each subcontractor’s work force. The narrative shall also include projections of the expected manning for each of the remaining weeks of the project, itemized by the Contractor’s work force and each subcontractor’s work force.
3. The Completion Schedule shall be updated by the Contractor at the end of each week to reflect actual progress and submitted to the Engineer on Tuesday of the following week together with new totals of remaining work and any revisions to the remaining week’s expected manning.
L. Products (Scheduling Software):
The scheduling software used by the Contractor shall be fully capable of importing/exporting data to/from Primavera P6, latest version. The proposed software shall be capable of transferring the information without degradation in the data, including but not limited to, scheduling logic and sequencing, activities, durations, resource loading, etc. The electronic file shall be submitted in .XER format.
SP-8.04 Progress Meetings
A. The Contractor shall attend weekly progress meetings with the Engineer. The meetings shall be attended by the Contractor's key project personnel. The overall status of the Contract shall be reviewed with particular attention to planned activities with special emphasis toward planned interruptions to existing utilities or services.
B. The Contractor shall prepare for each meeting a bar chart construction schedule depicting the work accomplished the previous week and planned activities for the upcoming two week period. This schedule shall be derived from the most recent statused progress schedule. Any deviations from this planned schedule shall be documented in writing and immediately brought to the attention of the Engineer. All deviations from this planned schedule shall be subject to the Engineer's review and approval.
SP-8.05 Construction Quality Control Plan
A. It shall be the responsibility of the Contractor to provide and maintain a Construction Quality Control Plan (hereinafter referred to as CQC Plan) for all work performed under the Contract. This requirement is in addition to any acceptance inspection and testing performed by the Engineer and/or his testing agencies. The CQC Plan shall conform to the requirements of this Special Provision. Within ten (10) days after issuance of the “Notice to Proceed” for the Contract, the Contractor shall submit an “Interim” CQC Plan to the Engineer for approval. The interim plan shall cover all work to be performed under the Contract during the first sixty (60) days of work. Further, within thirty (30) days after issuance of the “Notice to Proceed”, the Contractor shall submit a “Detailed” CQC Plan to the Engineer for approval. The detailed plan shall cover all work to be performed under the Contract. The Contractor's work may be suspended and progress payments may be withheld if the Contractor fails to submit conforming CQC Plans as scheduled herein.
B. In addition to the requirements detailed in this Special Provision, the CQC Plan shall incorporate all inspection and testing requirements detailed in the Technical Specifications for the Contract. The CQC Plan shall encompass all actions involving selection of construction material sources and suppliers, on-site and off-site fabrication of the Contractor-furnished items to be included in the work, on-site and off-site production of construction materials, work placement procedures, workmanship, inspection, and testing. The CQC Plan shall be designed and administered to assure that the Contractor’s work, including work performed by the Contractor’s suppliers and subcontractors, will be in full compliance with all applicable codes, technical specifications and plans under the Contract with respect to materials, workmanship, construction, finish, functional performance and identification.
C. With its Interim CQC Plan submission, the Contractor shall identify a qualified individual who shall be responsible for overall development and administration of the CQC Plan (CQC Plan Manager) and shall submit the proposed CQC Plan Manager’s qualifications to the Engineer for approval. The CQC Plan Manager shall report directly to an executive officer of the Contractor’s Company and shall have the necessary authority to discharge his/her responsibilities. The CQC Plan Manager shall visit the project site on a regular basis to assure proper administration of the CQC Plan. Depending on the nature and complexity of the work to be performed under the Contract and/or instances of non-conforming work, the Engineer may require the CQC Plan Manager to be on the project site on a full-time basis. For contracts in the amount of five million dollars ($5,000,000) or above, the CQC Plan Manager shall be on the project site on a full-time basis throughout the duration of the Contract, and shall have no other responsibilities than those required by this Special Provision.
D. With its Interim CQC Plan submission, the Contractor shall identify qualified individuals and firms responsible for inspection and testing of the work (CQC Plan Staff) and shall submit qualifications of the proposed CQC Plan Staff to the Engineer for approval. The CQC Plan staff shall be sufficient to inspect and test all items of work under the Contract as specified by this Special Provision. Members of the CQC Staff shall report directly to the CQC Plan Manager and shall have the necessary authority to discharge their responsibilities. For contracts in the amount of five million dollars ($5,000,000) or above, members of the CQC Plan Staff shall be on the project site on a full-time basis throughout the duration of the Contract, and shall have no other responsibilities than those required by this Special Provision. Further, for contracts in the amount of five million dollars ($5,000,000) or above, the CQC Plan Staff shall include qualified, dedicated, full-time inspectors, in addition to appropriate testing personnel, for each major work discipline performed under the Contract. These major work disciplines include, but are not limited to, civil, structural, structural steel, mechanical, electrical, and specialty work.
E. The Contractor’s Interim CQC Plan submission must include as a minimum the following:
1. An organization chart showing the portion of the Contractor's corporate organization that is concerned with the on-site construction activities;
2. The Contractor's on-site organization chart including its quality control organization;
3. Proposed personnel (CQC Plan Manager and CQC Staff) to be used in the quality control organization, personnel qualifications and experience, and the planned duration of their services;
4. Authority, duties and responsibilities of quality control personnel;
5. Operational procedures for accomplishing and reviewing work, supervision, inspections, tests, construction material production controls, fabrication controls, certifications, documentation of quality control operations, and inspections and tests, including those for subcontractors. These procedures shall include the methods to be utilized during the procurement cycle (order to delivery) for those items of materials or equipment which require source inspection, shop fabrication, and operations away from the work site;
6. Methods and procedures for selecting suppliers;
7. Methods and procedures for indoctrination and instruction of quality control personnel, construction supervisors, and foremen;
8. A copy of the letter of direction to the Contractor's representative and its staff for quality control which defines their delegated duties and responsibilities; and
9. When the quality control functions are to be accomplished by personnel not located at the site and/or not directly under the control of the CQC Plan Manager, the on-site/off-site coordinating procedures and authorities shall be covered in detail in the CQC Plan.
10. A detailed test and inspection plan keyed to the technical specifications, covering the work to be performed during the first sixty (60) days of work.
F. The Contractor’s Detailed CQC Plan submission shall include a detailed test and inspection schedule, keyed to the Technical Specifications, for each item of work. The test and inspection schedule shall cover all work to be performed under the Contract, including both on-site and off-site fabrication. The CQC Plan shall include as a minimum at least three (3) phases of inspection to be performed by the CQC Staff for all distinct items of work, as follows:
1. Preparatory inspections shall be performed prior to beginning each item of work. Preparatory inspections shall include a detailed review of Contract requirements and the CQC Plan test and inspection schedule for the item of work with the: Engineer, CQC Staff, Contractor’s Superintendent and subcontractor performing the work. Work shall not be permitted to proceed for any item of work that does not have an approved test and inspection schedule. Preparatory inspections shall also include: a check to assure that all materials and/or equipment have been tested, submitted, and approved; a check to assure that provisions have been made to provide required quality control testing; examination of the work area to ascertain that any work being built upon is complete and in conformance with Contract requirements; a physical examination of materials and equipment to assure that they conform to approved shop drawings or submittal data; and confirmation that all required materials and/or equipment are on hand.
2. Initial inspections shall be performed as soon as a representative portion of the particular item of work has been accomplished. The Engineer, CQC Staff, Contractor’s Superintendent and subcontractor performing the work, shall examine the representative portion of work to verify compliance with all Contract requirements, establish acceptable levels of quality and workmanship, review quality control testing and inspections for compliance with the Contract requirements and this Special Provision, confirm that defective, damaged or unapproved materials were not incorporated in the work.
3. Follow‑up inspections shall be performed by the CQC Staff, on a daily basis, to assure continuing compliance with the Contract requirements and established levels of quality and workmanship. Follow-up inspections shall confirm, on a daily basis, that defective, damaged or unapproved materials are not incorporated in the work.
4. The Engineer shall be notified at least forty-eight (48) hours in advance of each preparatory and initial phase inspection.
5. The CQC Plan Manager shall insure that all phases of inspection are made a matter of record in the CQC Plan documentation.
G. Approval of the Contractor’s CQC Plan shall not relieve the Contractor of its responsibility to comply with the requirements of the Contract Documents. The CQC Plan shall be revised or updated as directed by the Engineer. No additional cost or time extensions will be allowed for the Contractor's re-submission of rejected Interim and Detailed CQC Plans or for revisions or updating of the Detailed CQC Plan during the course of the Contract, as directed by the Engineer.
H. The Contractor shall provide and maintain gauges and other measuring and testing devices necessary to assure that articles conform to the Contract requirements. These devices shall be calibrated in accordance with national standards and certifications. Calibration certificates shall be maintained current and submitted to the Engineer. Any equipment exceeding its required re-calibration date or that becomes damaged or otherwise unreliable, shall be isolated, tagged, or otherwise marked to prevent its use without written permission of the Engineer.
I. The CQC Plan Manager shall take prompt action to correct conditions that have resulted or might result in nonconforming materials, parts, components, installations, or functions/operations. This action shall include preventive measures as well as correction of conditions that have occurred. The CQC Plan Manager shall document the nonconforming work and his/her efforts to correct the deficiencies and to minimize their future occurrence. Nonconformance Reports shall document corrective actions performed and be submitted to the Engineer for approval.
J. If the Contractor's work does not conform to the requirements of the Contract documents, the Engineer may issue a “Corrective Action” or “Nonconformance Report” to the Contractor. The Contractor must correct all deficiencies, or otherwise respond to the report, within seven (7) calendar days of issuance of the report by the Engineer. The Contractor shall not build upon or conceal any feature of the work containing uncorrected defects. If the work remains unresolved at the time of processing of the progress payment, the Engineer may withhold monies due to the Contractor until the deficiencies are corrected.
K. If the Engineer determines that the Contractor's CQC Plan and/or its administration are deficient in the identification and correction of nonconforming work, the Engineer shall issue a “CQC Plan Deficiency Notice” identifying the specific deficiencies and required corrective actions. The Engineer’s corrective actions may include modification of the CQC Plan, replacement of existing CQC Plan Staff or supplementing of CQC Plan Staff, all at no additional time or cost to the MAA. The Contractor shall correct all deficiencies in the CQC Plan as directed in writing by the Engineer. In the event that the Contractor fails to comply with the Engineer’s directions, the Engineer may withhold monies due to the Contractor until the deficiencies are corrected.
L. The CQC Plan Manager shall maintain current records for all inspections and tests performed throughout the life of the Contract, in a form approved by the Engineer. These records shall include, but not be limited to, factual evidence that the required inspections or tests have been performed, including type and number of inspections or tests involved, identification of inspectors and technicians, dates and results of inspections and tests, and deficient work identified including proposed remedial and corrective actions to be taken. These records must include statements that all supplies and materials permanently incorporated in the work are in full compliance with the Contract documents. Legible copies of these records must be furnished to the Engineer daily, or at such other intervals as directed. The records shall cover all work performed subsequent to the previously furnished records and shall be verified by the CQC Plan Manager
M. The CQC Plan Manager shall also prepare a monthly report, or at such intervals as directed by the Engineer, which summarizes all quality control operations. This summary report shall identify work performed, inspections made, tests performed, deficiencies found and corrective action taken during the month covered by the report.
N. All original quality control records shall be maintained in a central, on-site, location by the Contractor and turned over to the Engineer at the completion of the Contract.
O. The requirements to maintain quality control records, as described above, shall not be construed to relieve the Contractor from submitting samples, test data, shop drawings, material certificates, or other information required elsewhere in the Contract.
SP-8.06 Shop Drawings, Product Data, and Samples
A. General:
1. Shop drawings shall include, but are not limited to, drawings, diagrams and illustrations, material schedules, performance charts and data, product data and literature, technical specifications and test reports, engineering calculations, studies and reports and other data prepared by the Contractor, subcontractor, manufacturer, supplier, or distributor which illustrates how specific portions of the work shall be fabricated and/or installed. The Contract performance period outlined in the Contract Documents includes time for the review and approval of the Contractor's shop drawings. The Engineer's review of shop drawings, product/material samples, requested approved equals and substitutions shall be as follows:
a. Specified product/material samples (as defined below): twenty-one (21) calendar days minimum.
b. Shop drawings (as defined above): twenty-one (21) calendar days minimum.
c. Requests for approval of “Or Equal”, or “Approved Equal” articles pursuant to Special Provision: SP-5.03 or “Substitutions” pursuant to Special Provision: SP-5.04: forty-five (45) calendar days minimum.
d. Review time will begin and end with dates received by and returned from the Construction Manager.
e. The above minimum review times are to be used by the Contractor in developing the Detailed Schedule #1 required by Special Provision: SP-8.03.
B. Schedule of Shop Drawings and Submittal Register:
1. The Contractor shall be required to develop and maintain throughout the life of the project a Schedule of Shop Drawings and Submittal Register (hereinafter referred to as “Register”). The Register shall be submitted to the Engineer for approval with the Detailed Schedule #1 submission required by Special Provision: SP-8.03 and shall conform to the following requirements:
a. The Register shall be a comprehensive listing of each and every shop drawing (as defined by paragraph A above), product/material samples and other submissions required by the Contract documents.
b. Each item listed on the Register shall have a unique submittal number. The submittal number shall incorporate the relevant: Technical Specification, section and paragraph numbers, or relevant Contract: General or Special Provision, section and paragraph number, and applicable revision or version numbers.
c. The Register shall be developed and maintained in a spreadsheet format similar to the attached “Register Example Form”.
2. The Register shall indicate the Contractor’s required submittal date for each item listed. The Contractor’s required submittal date shall be determined as follows:
a. For submissions required by the General or Special Provisions, the Contractor’s required submittal date shall be calculated by adding the number of calendar days specified to the date of issuance of the “Notice of Recommended Award” or “Notice to Proceed” (whichever is applicable).
b. For shop drawings and product/material sample submissions, the Contractor’s required submittal date shall be calculated by taking the early installation date from the approved project CPM Schedule, subtracting the estimated procurement, fabrication and shipping duration, and subtracting the twenty-one (21) calendar day or forty-five (45) calendar day review time (whichever is applicable).
c. For those shop drawings that can reasonably be expected to have multiple submittals prior to approval, the required submittal date should also reflect the additional time necessary for a second cycle of submission and review.
3. The Register shall become a scheduling document and shall be used to control submittals throughout the life of the Contract. The Register and the Project CPM Schedule shall be coordinated by inserting the Register into the Project Schedule to form one complete scheduling document.
4. The Contractor shall carefully control his/her procurement operations to ensure that each individual submittal is made on or before the Contractor’s required submittal date shown on the Register. Failure by the Contractor to provide individual submittals on or before the Contractor’s required submittal date shown on the Register may result in extended review times, beyond the minimum review times detailed above. The Contractor shall be held responsible for any delays associated with extended review times in the event that the submittals are late.
5. The Contractor shall update the Register each month to show actual submission dates, days late (if any), review status and review action. The Contractor shall provide two (2) printed copies and one (1) diskette with electronic file format of the updated Register, which shall be submitted to the Engineer with the monthly Progress Schedule Update required by Special Provision SP-8.03.
C. Submissions:
1. Samples, drawings, specifications, catalogs, etc., submitted for approval shall be properly labeled indicating specific service for which materials or equipment are to be used including, section and article numbers of the Specifications governing, Contractor's name, and title of the Contract. Catalogs, pamphlets or other documents submitted to describe items on which approval is being requested shall be specific and identification in catalogs, pamphlets, etc., of the item submitted shall be clearly made in ink. Data of a general nature will not be accepted. Six (6) samples are required on finish color submissions.
2. Any costs incurred by the Contractor or the Administration due to the resubmittal of documents caused by inaccuracy, lack of coordination, and/or checking shall be the responsibility of the Contractor. Each variation from the Contract Specifications and Drawings shall be noted on the submittal. The Contractor shall also state the reason for such variations. If these requirements are not met, the submittal may be returned for corrective action.
D. Submittal Classification:
1. Administration Approved: Administration approval is required for extensions of design, critical materials, deviations, equipment whose compatibility with the entire system must be checked, and other items as designated by the Engineer. Within the terms of this Contract, they are considered to be "shop drawings".
2. Information Only: All submittals not requiring Administration approval will be for information only. They are not considered to be shop drawings as defined in Section A above.
3. Fire related shop drawings shall be submitted via the Engineer for review and approval by the Office of the Fire Marshal. Submit six (6) 22”x34” paper hard copies and one (1) CD containing a PDF of the same.
E. Schedule of Submission:
The Contractor shall submit for approval two (2) sepia reproducible and two (2) ozalid prints of shop drawings as called for in the Specifications or necessary for the work. If any contradiction exists between this requirement and the particular Specification, this requirement shall supersede. Send Shop Drawings to the organization designated by the Administration at the pre-construction meeting.
F. Certificates of Compliance:
Any certificates required for demonstrating proof of compliance of materials with specification requirements shall be executed in six (6) copies. Each certificate shall be signed by an official authorized to certify in behalf of the manufacturing company. The certificate shall contain the name and address of the Contractor, the project name and location, the quantity and date or dates of shipment or delivery to which the certificate applies. Copies of laboratory test reports submitted with certificates shall contain the name and address of the testing laboratory and the date or dates of the tests to which the report applies. Certification shall not be construed as relieving the Contractor from furnishing satisfactory material that meet the requirements of the specification.
G. Templates/Patterns:
The Contractor shall furnish all necessary templates, patterns, etc., for installing work, and for the purpose of making the general arrangement of the systems. All work included in the Drawings and details shall be consulted in connection with mechanical and electrical installations. Where the exact location of fixtures and equipment are not specifically located, the Contractor shall obtain this information in the field or from the Engineer.
H. Process of Approval:
The Engineer, on receiving sepia reproducible, will promptly approve them or indicate desired corrections, and return one (1) sepia of each drawing to the Contractor. The Contractor shall make all corrections and resubmit drawings, which are not approved in accordance with requirements for first submission. If the Contractor considers any correction indicated on the submittals to constitute a change to the Contract, notice as required under General Provision: GP-4.06-Changes, shall be given promptly to the Engineer.
I. Withholding of Payment:
Payment for materials incorporated in the work will not be made if required approval has not been obtained.
J. Interpretation:
Approval by the Engineer shall not be construed as a complete check but will indicate only that the general method of construction and detailing is satisfactory. Approval of drawings shall not be considered as a guarantee of measurements of building conditions. Where drawings are approved, said approval does not mean the drawings have been checked in detail; said approval does not in any way relieve the Contractor from his/her responsibility or necessity for furnishing material or performing work as required by the Contract Drawings and Specifications.
K. Use:
Use of shop drawings in fabrication or erection will not be permitted until approved, stamped, and dated by the Engineer. All shop drawings will be numbered consecutively by the Engineer when approved. Before submission for approval, drawings and schedules shall be fully checked by the Contractor for materials, sizes, dimensions, details, and shall bear evidence of the Contractor's verification and approval. All drawings shall be on same size sheets.
L. Distribution:
After approval of the shop drawings, the Contractor shall furnish prints to other Contractors furnishing work which will or may be affected by his/her work.
M. Work Prosecution:
The Contractor shall follow drawings in laying out work and check drawings of the various trades to verify spaces in which work will be installed. Maximum headroom and space conditions should be maintained, and where they appear inadequate, the Engineer shall be notified before proceeding with installations.
N. Construction Drawings:
If directed by the Engineer, the Contractor shall, without extra charge, make reasonable modifications in layout as needed to prevent conflict with work of other trades or for proper execution of the work. Detailed drawings of proposed departures due to actual field conditions or other causes shall be submitted to the Engineer for approval and any such changes shall be made without additional cost to the Owner.
O. Additional Materials and/or Equipment:
Because of the small scale of the drawings, it is not possible to indicate all offsets, fittings, and accessories, which may be required. The Contractor shall carefully investigate the structural and finish conditions affecting his/her work and shall arrange such work accordingly, furnishing such fittings, valves, transitions, pull or junction boxes, and accessories as may be required to meet such conditions at no additional cost to the Owner.
P. Variances:
Where variances occur between the Contract Drawings and Specifications or within either document itself, the item or arrangement of better quality, greater quality, or higher cost shall be included in the Contract Price. The Engineer will decide on the item and manner in which the work shall be installed.
Q. Time Extensions:
Failure by the Contractor to submit revised Shop Drawings in ample time for further review shall not entitle him to an extension of Contract time, and no claim for extension by reason of such default will be allowed.
R. Quality Control:
1. Source limitations. To the greatest extent possible for each unit of work, and subject to the restrictions of the Buy American Act, provide products, materials, or equipment of a singular generic kind from a single source.
2. Compatibility of Options. Where more than one choice is available as options for the Contractor's selection of a product or material, select an option that is compatible with other products and materials already selected. Total compatibility among options is not assured by limitations within the Contract Documents, but must be provided by the Contractor. Compatibility is a basic general requirement of product/material selections.
S. Product Delivery/Storage/Handling:
Deliver, handle, and store products in accordance with manufacturer's recommendations and by methods and means that will prevent damage, deterioration, and loss, including theft, and protect against damage from climatic conditions. Control delivery schedules to minimize long-term storage of products at the site and overcrowding of construction spaces and staging area. In particular, provide delivery/installation coordination to ensure minimum holding or storage times for products recognized to be flammable, hazardous, easily damages, or sensitive to deterioration, theft, and other sources of loss. Damaged or defective items, in the opinion of the Engineer, shall be replaced at no cost to the Administration.
T. Products:
1. General Product Compliance:
a. General. The compliance requirements for individual products, as indicated in the Contract Documents, are multiple in nature and may include generic, descriptive, performance, prescriptive, compliance with standards, conformance with graphic details, and other similar forms and methods of indicating requirements, all of which must be complied with.
b. Procedures for Selecting Products. The Contractor's options for selecting products are limited by Contract Document requirements and governing regulations, and are not controlled by industry traditions or procedures experienced by the Contractor on previous construction projects. Required procedures include, but are not necessarily limited to, the following for various indicated methods of specifying:
(1) Standards, Codes and Regulations. Where only compliance with an imposed standard, code, or regulation is required, selection from among complying products is the Contractor's option.
(2) Performance Requirements. Provide products that comply with specific performances indicated, and that are recommended by the Manufacturer (in published product literature) for the applications indicated. Overall performance of a product is implied where the product is specified with only certain specific performance requirements.
(3) Products Specified as Acceptable: Any products complying with the Specifications can be proposed whether listed specifically or not on the listing of acceptable products or manufacturers. Acceptable product items are listed for the convenience of the Contractor, but are not to be considered an all-inclusive list.
(4) Visual Matching. Where matching with an established sample is required, the Engineer will render the final judgement of whether a product proposed by the Contractor matches a sample satisfactorily.
(5) Visual Selection. Except as otherwise indicated, where specified product requirements include "... as selected from the Manufacturer's standard colors, patterns, textures..." or words of similar effect, the selection of manufacturer and basic product (complying with requirements) is the Contractor's option, and subsequent selection of color, pattern, and texture is the Engineer's selection. A phrase such as "...as selected from the Manufacturer's full color line..." means selection of standard or optional colors regularly produced by the selected manufacturer.
c. General Requirements for Electrical Work: The following applies to electrical work unless otherwise specified:
(1) Comply with the National Electrical Code.
(2) Conduits, Wiring and Equipment. Arrange generally as indicated. Any change resulting in a savings of labor or materials shall be made only in accordance with a contract change order. Deviations are permitted only where necessary to avoid interferences and only after drawings showing the proposed deviations have been submitted to and approved by the Engineer.
(3) Ratings. The motor horsepower and apparatus wattage ratings shown or specified are estimated values, and the corresponding sizes of feeders and other electrical equipment indicated to serve them are minimum sizes. Motors of greater horsepower and apparatus with larger wattage ratings may be furnished if necessary to meet the requirements of the various sections of the Specifications in which they are specified. Where larger motors or apparatus with larger wattage ratings are furnished, increase the capacity of the feeders and other electrical equipment serving them to correspond, at no additional cost to the Administration, in each case in which the Engineer determines that apparatus meeting the Specification requirements and requiring a horsepower or wattage not exceeding that listed is available from two or more sources.
2. General Product Requirements:
a. General. All equipment, material, and articles incorporated into the work covered by this Contract shall be new and of the most suitable grade for the purpose intended, unless otherwise specifically provided in the Contract. References in the specifications to equipment, material, articles, or patented processes by trade name, make, or catalog number, shall be regarded as establishing a standard of quality and shall not be construed as limiting competition. The Contractor may, at its option, use any equipment, material, article, or process that, in the judgement of the Engineer, is equal to that named in the Specifications, unless otherwise specifically provided in the Contract. Provide products that are undamaged and unused at the time of installation, and that are complete with accessories, trim, finish, safety guards, and other devices and details needed for a complete installation and is suitable for the intended use and effect.
b. Standard Products. Products shall be essentially the standard catalogued products of manufacturers regularly engaged in production of such products and shall be the manufacturers' latest standard design that complies with the Specification requirements. Equipment shall essentially duplicate items that have been in satisfactory commercial and industrial use at least two (2) years, or more if otherwise specified, prior to bid opening; or, in lieu thereof, shall have been used and operated in a test installation that, in the opinion of the Engineer, duplicates its field performance for the same period of time. The Engineer reserves the right to require the Contractor to submit evidence of this effect for approval. When two units of that same class of equipment are required, these units shall be the product of a single manufacturer; however, the component parts of the system may not require to be the products of the same manufacturer.
c. Continued Availability. Products that, by nature of their application, are likely to be needed at a later date for maintenance and repair or replacement work shall be current models for which replacement parts are available.
U. Working Drawings for Falsework Systems:
1. Falsework systems plans (design and construction) shall be the responsibility of the Contractor. A copy of the plans and calculations shall be submitted to the Engineer for information only.
2. The Contractor shall utilize a Professional Engineer (PE) registered in the State of Maryland who has a minimum of five years experience in falsework design. The falsework design calculation and plans shall be signed by the PE and bear the seal of the PE. The submittal of the design and falsework plans shall include the PE's resume showing evidence of the required experience.
3. The Contractor's plans and design calculations shall evaluate and qualify all products and components including manufactured products and proprietary items for their intended service.
4. Every structure in the Contract will require a separate falsework design analysis, separate plans and design submittals as set forth above. This applies even though structures may appear to be identical.
5. Each falsework system shall be designed to have the capacity to support all vertical and horizontal loading with enough redundancy to prevent progressive failure. Vertical loading, differential settlement forces, live load where applicable and all horizontal lateral and longitudinal forces shall be taken into account. Unbalanced temporary loading caused by placement sequence shall also be provided for in the design. Adequate diagonal bracing in all planes shall be employed.
6. All falsework systems designs and plans shall provide for adequate foundations with bearings below the frost line or on rock or on piling and for possible settlement. If additional subsurface data is necessary, it shall be obtained and analyzed for proper design of the plans and performance of construction.
7. Falsework designs and plans shall include protection against impact from uncontrolled highway vehicles, accidental collision of a crane boom, or other construction equipment and vehicles, traffic vibration, flood waters, high winds, and any other envisioned contingent situations.
SP-8.07 Notice to the MAA of Labor Disputes
A. If the Contractor has knowledge that any actual or potential labor dispute is delaying or threatens to delay the timely performance of this Contract, the Contractor shall immediately give written notice, including all relevant information, to the Engineer.
B. The Contractor agrees to insert the substance of this clause in all subcontracts which are entered into under this Contract. All subcontractors shall be required to immediately notify the next higher tier subcontractor or the Prime Contractor of any actual or potential labor disputes that may affect, delay, or threaten the timely completion of this Contract.
SP-8.08 Record Drawings/As-Built Drawings
A. The Contractor shall set aside at the site one (1) set of Contract Drawings to be used as the Project Record Drawings. The Contractor shall record on the Project Record Drawings all changes to show "As-Built" conditions. The Contractor shall also be responsible to assure that all changes made by his/her subcontractors be accurately shown as to the actual installation of all their work. Items to be included, but not limited to, are changes in sizes, grades, locations, and dimensions for all underground pipes, conduits, cables, valves, junctions, connections, and ends. All valves shall be numbered to correspond to valve tags and incorporated on printed lists.
B. In addition to the above-mentioned Record Drawings, the Contractor shall also provide and maintain on the job, in good order, a complete set of "As-Built" Drawings showing all changes made to the Contract Drawings during the entire construction period under this Contract. Upon completion of the work, this set of drawings, complete and up to date, shall be turned over to the Engineer.
C. The as-built drawings will be jointly inspected for accuracy and completeness by the Engineers representative and the Contractor's representative prior to submission of each monthly pay estimate.
D. The as-builts documents, including all attachments, shall be submitted to the Engineer electronically in a single PDF file along with a hard copy. The Contractor shall prepare the as-built prints and pdf files for delivery to the Engineer at the time of Final Inspection for review and approval. These as-built marked pdf files and hard copy prints shall be neat, legible and accurate. If, upon review, the drawings and documents are found to contain errors and/or omissions, they shall be returned to the Contractor for corrections. The Contractor will be liable for costs incurred by the MAA in regards to resources expended in the preparation of the necessary corrections. The Contractor shall complete the corrections and return the as-built marked pdf and prints to the Engineer within ten (10) calendar days of being notified.
E. The Contractor's work may be suspended or payments may be withheld if the Contractor fails to maintain updated Project Record Drawings, or to submit the required "as-built" drawings as indicated above, subject to the satisfaction and approval of the Engineer.
SP-8.09 Project Completion and Punchlists
A. Prior to or at the Final Inspection for acceptance of the Contract or portion/phase of the Contract, a punchlist will be developed by the MAA to identify items of work remaining to be completed, unacceptable, or defective. The Contractor shall have time allotted to complete the punchlist that shall be equal to ten (10) percent of the original Contract time plus ten (10) percent of any time added by change orders. When the project is to be performed in phases as required by the Contract Specifications, the Contractor shall be allotted ten (10) percent of the specified time for each phase. The time shall begin on the date of notice, when served prior to final acceptance, or on the day of final acceptance for the entire Contract or any portion or phase of the Contract as applicable. Any portion of a day shall be counted as a full day.
B. The Contractor is hereby advised that once the facility has been “Accepted for Maintenance” by the MAA, access to the facility for performance of punchlist work must be coordinated with the MAA and Airport Tenants and shall be subordinate to MAA and Airport Tenant operational and security requirements.
C. Failure by the Contractor to complete any punchlist items in the allotted time may result in the MAA causing the incomplete punchlist items to be completed by others, without further notice to the Contractor.
D. In the event that the MAA has incomplete punchlist items completed by others pursuant to Paragraph C above, the Contractor shall be assessed all direct costs incurred by the MAA plus an administrative fee equal to thirty percent (30%) of the direct costs. The MAA shall deduct said direct costs and administrative fee from any monies due or to become due the Contractor under this Contract.
E. In the event that the MAA allows the Contractor to continue work on punchlist items beyond the allotted time, the MAA shall deduct from any monies owed Contractor, all construction management and inspection costs it incurs as a result of the work being performed beyond the allotted time.
F. Warranties shall be in effect from the date of final acceptance for maintenance pursuant to GP-5.13, Acceptance for Maintenance.
G. Notwithstanding General Provision: GP-8.09-Liquidated Damages, and as may be specified elsewhere in the Contract, the Contractor shall pay, indemnify, and save harmless the MAA from all suits, actions, claims, demands, damages, losses, expenses, and/or costs of every kind and description to which the MAA may be subjected to resulting from non-completion of the Contract which negatively affects separate Contractors on adjoining or overlapping work. The whole or so much monies due or become due the Contractor under the Contract, as may be considered necessary by the MAA, may be retained by the Administration until such suits or claims for damages shall have been settled, or otherwise disposed of, and satisfactory evidence to that effect furnished to the Procurement Officer. This obligation is not limited by, but is in addition to, the Performance Bonds contained in the Contract.
SP-8.10 Time Extensions for Unusually Severe Weather
A. Paragraph D.1. In order for the Engineer to award a time extension under this clause, the Engineer must be satisfied that the following conditions exist.
1. The weather experienced at the project site during the Contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month;
2. The unusually severe weather must actually cause a delay to the completion of the Contract. The delay must be beyond the control and without the fault or negligence of the Contractor.
3. Time extensions for unusually severe weather occurring beyond the contractual completion date will not be granted if the contract duration has extended beyond the contractual completion date due to Contractor delay.
B. The following schedule of monthly anticipated adverse weather delays is based on National Oceanic and Atmospheric Administration (NOAA) or similar data for the project location and will constitute a baseline for monthly weather time evaluations. The Contractor's progress schedule must reflect these anticipated adverse weather delays in all weather dependent activities.
Monthly Anticipated Adverse Weather Delays
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
8 7 7 8 8 7 5 6 4 6 5 5
C. Upon issuance of the NTP and continuing throughout the Contract, the Contractor will record on the daily CQC Report, the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for fifty percent (50%) or more of the Contractor's scheduled work day. The number of actual adverse weather delay days shall include days impacted by actual adverse weather to be calculated chronologically from the first to the last day of each month, and be recorded as full days. If the number of actual adverse weather delay days exceeds the number of days anticipated above, the Engineer will convert any qualifying delays to calendar days and issue a time extension in accordance with the General Provisions Section GP-8.08, Termination for Default - Damages for Delay - Time Extensions and SP-8.03 Critical Path Method Schedule. Time extensions for unusually severe weather shall not be compensable.
SP-8.11 Operating and Maintenance Data
The Contractor shall submit to the Engineer, when the project is forty percent (40%) complete, a list of proposed maintenance and instruction manuals to be furnished to the Administration, and the scheduled dates of all required field instruction to be provided by the Contractor-furnished personnel or the Manufacturer's representatives. All maintenance and instruction manuals must be furnished to the Engineer at least two weeks prior to the scheduled dates of any required Contractor-furnished field instructions or at least one month prior to project completion, if no Contractor-furnished field instructions are required.
SP-8.12 Order of Precedence of Specifications/Standard Provisions/Plans
The order of precedence of contract documents shall be as follows:
1. Bid Forms
2. General Provisions
3. Special Provisions
3. Technical Specifications
4. Drawings
In the event of a conflict between contract documents, the earlier listed above shall prevail.