5.5 Construction Safety and Phasing Plans
Projects receiving funding from the Airport Improvement Program (AIP) or the Passenger Facility Charge (PFC) program must prepare a Construction Safety and Phasing Plan (CSPP). All CSPP shall be prepared in accordance with the latest FAA AC 150/5370-2 and approved and signed by the Director of Airport Operations for BWI Marshall Projectsand the Chief of Airport Operations at Martin State Airport for all MTN projects. The document shall be prepared based on a joint effort between MDOT MAA Operations, the ATCT, MDOT MAAOffice of Engineering & Construction and the Consultant.
5.5.1 CSPP Review Checklist
Refer to Volume 5, Section 2.4.1.
5.5.2 Design Progress Milestones
Refer to Volume 5, Section 2.4.2.
5.5.3 Sample CSPP
Refer to Volume 5, Section 2.4.3.
5.5.4 Specific Design Requirements
5.5.4.1 Placement of Construction Barricades
CSPP shall require that no spaces be permitted between adjacent barricades.